Industrial lead times
Find the long-lead part before it sets your schedule.
Rochester Public Utilities recorded 22–36 weeks across its January 2026 bids for four 15 kV cable specifications. Albertville’s domestic 36-inch butterfly valve quote was 30–38 weeks in its May 2026 filing. Compare dated bids, reported deliveries and factory estimates, with a source excerpt for each reading.
Public readings 73
| 665 mm forged steel disc for Flender | Forgings | 2026-09-14 | 41 | 4 weeks | Reported delivery | Siderforgerossi Group | 2026-11-28 |
|---|---|---|---|---|---|---|---|
| 665 mm forged steel disc for Flender, standard | Forgings | 2026-09-14 | 81 | 8 weeks | Supplier benchmark | Siderforgerossi Group | 2026-11-28 |
| Medium- and low-voltage switchgear | Switchgear | 2026-Fall | 521 | 52+ weeks | Market report | Skanska USA Building | 2026-11-28 |
| Nonstandard imperial-shaft gearmotor | Motors | 2026-07-13 | 41 | 4+ weeks | Supplier estimate | ACORN Industrial Services | 2026-11-28 |
| Alternate domestic 36-inch butterfly valve, first quote | Valves | 2026-05-04 | 461 | 46 weeks | Public bid | Municipal Utilities Board of Albertville | 2026-11-28 |
| Alternate domestic 36-inch butterfly valve, second quote | Valves | 2026-05-04 | 301 | 30–36 weeks | Public bid | Municipal Utilities Board of Albertville | 2026-11-28 |
| Alternate domestic 36-inch butterfly valve, third quote | Valves | 2026-05-04 | 301 | 30–36 weeks | Public bid | Municipal Utilities Board of Albertville | 2026-11-28 |
| Domestic 36-inch ductile-iron butterfly valve | Valves | 2026-05-04 | 301 | 30–38 weeks | Public bid | Municipal Utilities Board of Albertville | 2026-11-28 |
| Imported 36-inch ductile-iron butterfly valve | Valves | 2026-05-04 | 61 | 6–8 weeks | Public bid | Municipal Utilities Board of Albertville | 2026-11-28 |
| Steel casting plant backlog after sharp demand declines | Castings | 2026-03-23 | 61 | 6–8 weeks | Backlog | Steel Founders’ Society of America | 2026-11-28 |
| Steel casting plant backlog in normal conditions | Castings | 2026-03-23 | 81 | 8–10 weeks | Backlog | Steel Founders’ Society of America | 2026-11-28 |
| WESCO 1/0 15 kV primary cable, 24,000 ft | MV cable | 2026-02-12 | 81 | 8–10 weeks | Public bid | City of Concord, North Carolina | 2026-11-28 |
| Border States / Prysmian — 15 kV 1/0 solid aluminum cable in duct | MV cable | 2026-01-30 | 301 | 30–32 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| Border States / Prysmian — 15 kV 1/0 solid jacketed aluminum cable | MV cable | 2026-01-30 | 241 | 24–26 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| Border States / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 241 | 24–26 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| Border States / Prysmian — 15 kV 750 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 241 | 24–26 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| IRBY / Okonite — 15 kV 1/0 solid aluminum cable in duct | MV cable | 2026-01-30 | 321 | 32–34 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| IRBY / Okonite — 15 kV 1/0 solid jacketed aluminum cable | MV cable | 2026-01-30 | 301 | 30–32 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| IRBY / Okonite — 15 kV 4/0 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 341 | 34–36 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| IRBY / Okonite — 15 kV 750 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 261 | 26–28 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| RESCO / Prysmian — 15 kV 1/0 solid aluminum cable in duct | MV cable | 2026-01-30 | 311 | 31–33 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| RESCO / Prysmian — 15 kV 1/0 solid jacketed aluminum cable | MV cable | 2026-01-30 | 251 | 25–27 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| RESCO / Prysmian — 15 kV 4/0 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 251 | 25–27 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| RESCO / Prysmian — 15 kV 750 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 251 | 25–27 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| WESCO / CME — 15 kV 1/0 solid aluminum cable in duct | MV cable | 2026-01-30 | 321 | 32–34 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| WESCO / CME — 15 kV 1/0 solid jacketed aluminum cable | MV cable | 2026-01-30 | 301 | 30–32 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| WESCO / CME — 15 kV 4/0 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 341 | 34–36 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| WESCO / CME — 15 kV 750 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 261 | 26–28 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| WESCO / LS Cable — 15 kV 1/0 solid aluminum cable in duct | MV cable | 2026-01-30 | 261 | 26 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| WESCO / LS Cable — 15 kV 1/0 solid jacketed aluminum cable | MV cable | 2026-01-30 | 221 | 22 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| WESCO / LS Cable — 15 kV 4/0 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 221 | 22 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| WESCO / LS Cable — 15 kV 750 stranded jacketed aluminum cable | MV cable | 2026-01-30 | 221 | 22 weeks | Public bid | Rochester Public Utilities | 2026-11-28 |
| Air-cooled chillers | HVAC equipment | 2026-Q1 | 141 | 14–23 weeks | Market report | Gilbane Building Company | 2026-11-28 |
| Commercial-grade air handling units | HVAC equipment | 2026-Q1 | 161 | 16–20 weeks | Market report | Gilbane Building Company | 2026-11-28 |
| Custom air handling units | HVAC equipment | 2026-Q1 | 201 | 20–33 weeks | Market report | Gilbane Building Company | 2026-11-28 |
| Low-voltage switchgear | Switchgear | 2026-Q1 | 321 | 32–54 weeks | Market report | Gilbane Building Company | 2026-11-28 |
| Medium-voltage switchgear | Switchgear | 2026-Q1 | 491 | 49–82 weeks | Market report | Gilbane Building Company | 2026-11-28 |
| Rooftop HVAC units above 50 tons | HVAC equipment | 2026-Q1 | 131 | 13–22 weeks | Market report | Gilbane Building Company | 2026-11-28 |
| Rooftop HVAC units below 50 tons | HVAC equipment | 2026-Q1 | 121 | 12–18 weeks | Market report | Gilbane Building Company | 2026-11-28 |
| Water-cooled chillers above 1,000 tons | HVAC equipment | 2026-Q1 | 281 | 28–44 weeks | Market report | Gilbane Building Company | 2026-11-28 |
| Water-cooled chillers below 1,000 tons | HVAC equipment | 2026-Q1 | 181 | 18–30 weeks | Market report | Gilbane Building Company | 2026-11-28 |
| Price, Utah, 16 × 4 ft box culvert | Precast | 2025-10-23 | 61 | 6–7 weeks | Public bid | Geneva Pipe Company | 2026-11-28 |
| Cold Springs Road concrete box culvert | Precast | 2025-10-07 | 81 | 8 weeks | Buyer estimate | City of West Point, Utah | 2026-11-28 |
| Power Line / Okonite 500 MCM Cu URD MV cable, 15 kV | MV cable | 2025-08-04 | 81 | 8–10 weeks | Public bid | City of Portland, Michigan | 2026-11-28 |
| RESCO / Kerite 500 MCM Cu URD MV cable, 15 kV | MV cable | 2025-08-04 | 101 | 10 weeks | Public bid | City of Portland, Michigan | 2026-11-28 |
| Bonfiglioli motor with nonstandard flange | Motors | 2025-07-22 | 81 | 8 weeks | Supplier estimate | ACORN Industrial Services | 2026-11-28 |
| 5 hp IE3 premium-efficiency motor | Motors | 2025-01-02 | 21 | 2 weeks | Supplier benchmark | CalNEXT | 2026-11-28 |
| Commonly stocked 1–20 hp motors | Motors | 2025-01-02 | 11 | 1–2 weeks | Pilot benchmark | CalNEXT | 2026-11-28 |
| Custom-order advanced motor | Motors | 2025-01-02 | 61 | 6 weeks | Reported wait | CalNEXT | 2026-11-28 |
| IE4 motors from surveyed manufacturer | Motors | 2025-01-02 | 21 | 2–4 weeks | Supplier benchmark | CalNEXT | 2026-11-28 |
| Large nuclear forgings | Forgings | 2024-02 | 104.41 | 24–48 months | Workshop estimate | US Department of Energy | 2026-11-28 |
| Atomac AKH2 PFA 2-inch ductile-iron ball valve | Valves | 2024-01-22 | 41 | 4 weeks | Factory estimate | Flowserve | 2026-11-28 |
| Atomac AKH2 PFA 4-inch ductile-iron ball valve | Valves | 2024-01-22 | 121 | 12 weeks | Factory estimate | Flowserve | 2026-11-28 |
| Atomac AKH2A PFA 4-inch ductile-iron ball valve | Valves | 2024-01-22 | 181 | 18 weeks | Factory estimate | Flowserve | 2026-11-28 |
| Durco BTV 2–12-inch TFE-lined butterfly valves | Valves | 2024-01-22 | 181 | 18 weeks | Factory estimate | Flowserve | 2026-11-28 |
| 16-inch metal-seated ball valve via TIPS contract | Valves | 2023-10-12 | 321 | 32–36 weeks | Delivery commitment | City of Georgetown, Texas | 2026-11-28 |
| Municipal Valve 16-inch metal-seated ball valve | Valves | 2023-10-12 | 401 | 40–44 weeks | Public bid | City of Georgetown, Texas | 2026-11-28 |
| Medium-voltage cable | MV cable | 2023-Spring | 301 | 30–45 weeks | Market report | Skanska USA Building | 2026-11-28 |
| Main water injection valve, expedited delivery | Valves | 2022-11-22 | 201 | 20 weeks | Reported delivery | Severn | 2026-11-28 |
| Main water injection valve, standard replacement | Valves | 2022-11-22 | 301 | 30 weeks | Supplier benchmark | Severn | 2026-11-28 |
| Water injection valve trim, expedited delivery | Valves | 2022-11-22 | 121 | 12 weeks | Reported delivery | Severn | 2026-11-28 |
| Water injection valve trim, standard lead | Valves | 2022-11-22 | 221 | 22 weeks | Supplier benchmark | Severn | 2026-11-28 |
| Medium-voltage switchgear | Switchgear | 2022-Summer | 181 | 18–24 weeks | Market report | Skanska USA Building | 2026-11-28 |
| Nonstock 5–15 kV cable | MV cable | 2022-Summer | 141 | 14–20 weeks | Market report | Skanska USA Building | 2026-11-28 |
| McCann Concrete Products 8 × 6 ft box culvert sections | Precast | 2022-05-17 | 13.41 | 94 days | Public bid | City of Lebanon, Missouri | 2026-11-28 |
| Scurlock Industries box culvert bid, 291 linear ft | Precast | 2022-05-17 | 141 | 14–20 weeks | Public bid | City of Lebanon, Missouri | 2026-11-28 |
| Volume purchase of 5 kV cable | MV cable | 2022-Spring | 201 | 20–28 weeks | Market report | Skanska USA Building | 2026-11-28 |
| Foundry backlogs in 2021–2022 | Castings | 2021–2022 | 201 | 20+ weeks | Backlog | State Line Foundries | 2026-11-28 |
| Reverse-engineered high-strength steel castings | Castings | 2016-08-12 | 31 | 3 weeks | Reported production | Foundry Management & Technology | 2026-11-28 |
| Steel casting best-practice example | Castings | 1998-01 | 41 | 4 weeks | Industry benchmark | Cast Metal Coalition | 2026-11-28 |
| Steel casting procurement | Castings | 1998-01 | 201 | 20–40 weeks | Industry benchmark | Cast Metal Coalition | 2026-11-28 |
| New forging orders in the US industry survey | Forgings | 1992-12 | 39.31 | 39.3 weeks | Historical survey average | US Department of Commerce | 2026-11-28 |
| Repeat forging orders in the US industry survey | Forgings | 1992-12 | 15.41 | 15.4 weeks | Historical survey average | US Department of Commerce | 2026-11-28 |
Lead times by category
Supply the monthly index
Send one fixed-spec shipment estimate each month. Buyers get a benchmark they can put on a schedule.
Read the specifications and join the panelRequest quotes
Send the part specification, quantity, delivery ZIP code and deadline to the procurement desk.
Request received by the procurement desk.
If the form fails, email desk@industrialleadtimes.com with your brief.
Lead-time questions
What kind of lead time does each row show?
Each row gives the source’s clock. A bid records a proposed wait, a delivery records the reported outcome, and backlog measures queued work. Open the reading to see which milestone the publisher used.
Which readings belong side by side?
Start with the same specification, reading type and start milestone. The Rochester cable rows let you compare separate supplier quotes against the same numbered bid item.
Where do the monthly index figures come from?
The first monthly figure requires five independent suppliers to quote the same specification. Until that threshold is met, use the dated public readings to plan a purchase.